Declare the equipment package once. AV Stage Tools turns it into station power, outlets and breakouts, signal cable stock, long-run transport checks, generators, LAN switching, PoE, wireless capacity and fiber uplinks.
01shared production modelNAMEPLATES + ROUTES REQUIRED
FIRST-PARTY SETTINGS COOKIENo temporary settings cookie found
Saves compact planner assumptions for 90 days on this browser. It does not store equipment lists, routes, names, email addresses, analytics or advertising identifiers.
01 · Package
Equipment and station map
The example matches the requested 48-panel wall, two line-array hangs, eight subs and an audio station. Zero-watt rows are intentionally blocked until you enter exact nameplate data.
Hierarchy: Production → venue → event date → room/stage → department/system → equipment and connections. These identifying fields stay out of the temporary cookie.
PLANNING MODEStart with an event package, then replace every assumption.
Presets provide common device relationships, not a rental recommendation or approved equipment list.
Choose a profile to replace the example with a complete editable starting package.
Selected reference: Record software, codecs, output format, redundancy and storage; replace the 850 W allowance with the complete computer's measured/nameplate data. Published specification ↗
02 · Engineering graph
Explainable compatibility
Connector shape and carried signal are separate facts. Every result states why it passed, what infrastructure is missing and which exact manufacturer values still need verification.
The declared connector and 12G-SDI transport match, subject to the listed system conditions.
VERIFY BEFORE RELEASE
verified cable-distance/format rating
matching reference and frame format
MODEL RULESUnknown stays unknownManufacturer data outranks assumptionsEvery warning explains the correctionNo passive-cable fiction
03 · Distribution
Power outlets, breakouts and feeders
Breakouts solve physical outlet distribution. The user-entered outlet-circuit assumption converts declared load into distribution counts; AV Stage Tools does not select breakers and never treats extra outlets as extra amperage.
Known running load0 W4 nameplate entries still missing
Branch circuits020 A at 80% planning use
Main feeder runs06 circuits carried per declared feeder
Breakout boxes14outlet count and circuit count both covered
Generator floor0 / 0 kVAcontinuous / simultaneous peak · 0 kVA peak average per generator
INPUT REQUIRED: Enter nameplate watts for Video wall: LED panels, Stage audio: Line-array hangs, Stage audio: Subwoofers, Audio station: Audio station devices. Circuit, generator and voltage-drop results currently include known loads only.
STATION
Video wall
Equipment
48
Known load
0 W
Outlets
48 + spare = 58
Breakouts
10
Circuits
0
Main feeds
0
Enter nameplate watts to calculate the run.
STATION
Stage audio
Equipment
10
Known load
0 W
Outlets
10 + spare = 12
Breakouts
2
Circuits
0
Main feeds
0
Enter nameplate watts to calculate the run.
STATION
Audio station
Equipment
10
Known load
0 W
Outlets
10 + spare = 12
Breakouts
2
Circuits
0
Main feeds
0
Enter nameplate watts to calculate the run.
04 · Signal inventory
Cable stock, snakes and feed groups
“Units per feed” captures daisy chains and processor capacity. Set it from the exact panel, amplifier, network or controller documentation.
Ethernet data1816 working feeds · 2,365 ft stock with spare/slackXLR / AES audio86 working feeds · 1,046 ft stock with spare/slackXLR / AES capacity1 × 168 packed feeds · 16 channels available · 165 ft longest individual feed with route slack. Profile states whether these are analog trunks or local stage-box fan-outs.Ethernet port blocks124-port capacity blocks; full network topology below
05 · Long runs
Resolution, distance and active handoffs
A digital format does not automatically downgrade cleanly at a universal distance. AV Stage Tools uses a published standard limit where one exists, otherwise it requires the exact product’s tested 4K and 1080p limits.
SPEC REQUIREDNo exact format-distance limit enteredHDMI defines performance and certification, not one universal cable-length limit. Enter the exact cable and equipment limits.
Single-link limit
Exact spec needed
boosters / extender relay points
Enter exact limit
Paths to pack
2
Total route stock
2,200 ft
Use a manufacturer-rated optical HDMI or video-over-fiber system. Do not assume cascaded boosters will preserve format or HDCP.
06 · Network package
LAN, wireless, video and control
Build the event network from endpoints and traffic—not a guessed switch count. Video, camera, wall-control, audio, PoE and wireless devices remain visible by VLAN and bandwidth demand.
Managed switches240 planned device ports with 20% spare
Copper drops4080 patch cords, two per terminated drop
Access-point quantity is a client-capacity floor, not a coverage design. Confirm RF survey, interference, channel plan, antenna pattern, mounting, PoE wattage, switch fabric, multicast/IGMP behavior, protocol compatibility, cybersecurity and venue policy with qualified network personnel.
07 · Display audience analysis
Viewing distance, pitch, image size and brightness
The venue audience depth populates the farthest viewer and the selected LED equipment record names the product. All calculations use the same engine as the standalone display tool.
ENGINEERING RESULT · AV Stage Tools display-viewing 1.0.0 · 2026-08-14
Four questions. Separate answers.
No single green check hides an unknown manufacturer value or environmental measurement.
Nearest viewer18.0 ft
Maximum pitch
1.596 mm
Selected pitch
1.9 mm
FAILFarthest viewer150.0 ft
Minimum image height
15.0 ft
Selected height
14.1 ft
FAILPixel density1.9 mm
Linear
526.32 px/m
Area
277,008 px/m²
Density
13.37 PPI
Wall resolution4096 × 2304
Total
9.44 MP
Source
manufacturer cabinet resolution
PASSBrightnessUNKNOWN
Selected operating
unknown
Reflected ambient
unknown
UNKNOWN
Pixel visibilityFAIL
Far-view legibilityFAIL
Native resolutionPASS
BrightnessUNKNOWN
Viewing angleREVIEW REQUIRED
SCREENAudience distance cross-section
Visible-pixel risk
Preferred / evaluate legibility
Pixel threshold 21.4 ftNearestMedianFarthest
80% of modeled audience-zone weight is pixel-pitch compliant. This three-zone strip is a planning view; exact seating polygons and seat-level heat maps remain a future geometry extension.
SCREEN DOOR / VISIBLE PIXEL STRUCTURE
1.191 arcminutes
Internally treated as individual pixel/pixel-structure visibility. Threshold: 1 arcminute(s). Visual-acuity distance for 1.9 mm: 21.4 ft. Maximum pitch for the entered front row: 1.596 mm.
FAR-VIEW IMAGE CLARITY
5.3818° vertical image
428.1 pixels/degree vertically. The smallest critical element is 5% of image height and occupies 16.157 arcminutes for the back row.
RECOMMENDED PITCH RANGE
1.2–1.56 mm
Maximum mathematically acceptable pitch: 1.596 mm. The shown range uses common nominal pitch references only—not verified product availability. Reviewed catalog matching remains empty until real product records are connected.
PRODUCT MATCHING
No reviewed catalog connected
The entered product is analyzed, but ranked candidates remain empty until manufacturer records contain pitch, cabinet resolution, brightness, viewing angle, power, weight and inventory.
BUILD THIS WALL · entered cabinet data
16 × 9144 cabinets + 8 spares
4096 × 23049.44 MP actual entered cabinet raster
Power unknownmanufacturer weight required
Processor unknownprocessor capacity required
Review required
Brightness verification incomplete: ambient illuminance at the screen surface, display-surface reflectance required.
Manufacturer viewing-angle data is missing.
Formulas, assumptions and source references
Pixel angle: 2 × atan(p ÷ 2D). Maximum pitch: 2 × D × tan(θ ÷ 2). Ambient reflection: lux × reflectance ÷ π. The brightness model assumes simplified Lambertian reflection and compounds user-entered reserves.
BDM/ADM calculations follow AVIXA's publicly documented acuity-factor concepts; AV Stage Tools does not claim formal standard certification.
Public methodology reference: Entertainment Video / IMAG · Basic Decision Making · Analytical Decision Making.
These checks belong with the production model because their results affect routes, equipment, network and crew preflight—not as disconnected calculators.
Camera systems · preflight
Multi-Cam Sync Planner
Declare the production standard once, compare every camera, then perform and review a recorded clap/flash sync test.
Settings aligned
Record and review a clap or flash test before rolling.
Matching menu labels does not prove synchronization. Confirm reference cabling, format, timecode jam stability and recorded sync on the exact equipment chain.
09 · Commercial handoff
Material takeoff and client quote worksheet
Calculated equipment, cabling, distribution and network quantities flow into one pricing worksheet. Internal cost and markup stay out of the printable client view.
TAKEOFF LINES16
CLIENT TOTAL$0.00
RATES NEEDED18
LOCAL SAVEDevice-local draft
Takeoff item
Qty
Length
Rate basis
Internal cost
Markup
Client total
Show
LED / Display · Video wallLED panelsEnter exact panel model · Enter connector / adapter chainNameplate load missing; power totals are incomplete.
48 ea
—
Rate needed
Audio · Stage audioLine-array hangsEnter powered/passive model · Enter connector / adapter chainNameplate load missing; power totals are incomplete.
2 ea
—
Rate needed
Audio · Stage audioSubwoofersEnter powered/passive model · Enter connector / adapter chainNameplate load missing; power totals are incomplete.
8 ea
—
Rate needed
Audio · Audio stationAudio station devicesEnter console, computer and outboard models · Enter connector / adapter chainNameplate load missing; power totals are incomplete.
10 ea
—
Rate needed
Power distribution · Video wallPower breakout / outlet distributor58 outlets planned · 0 calculated branch circuits
10 ea
—
Rate needed
Power distribution · Stage audioPower breakout / outlet distributor12 outlets planned · 0 calculated branch circuits
2 ea
—
Rate needed
Power distribution · Audio stationPower breakout / outlet distributor12 outlets planned · 0 calculated branch circuits
2 ea
—
Rate needed
Signal cabling · Project-wideEthernet data16 working feeds + packed spare allowance
18 cable
2,365 ft
Rate needed
Signal cabling · Project-wideXLR / AES audio6 working feeds + packed spare allowance
8 cable
1,046 ft
Rate needed
Audio distribution · Project-wideXLR / AES snake capacity block16-channel block · 8 packed feeds / 16 available channels
1 ea
165 ft
Rate needed
Network · Project-wideManaged production network switch22 usable device ports per planned switch
Network cabling · Project-wideNetwork patch cordTwo patch cords per packed copper drop
80 ea
—
Rate needed
Network cabling · Project-wideFiber pair2 working links including declared redundancy
3 pair
—
Rate needed
Network · Project-wideMatched optical transceiver endpointVerify speed, wavelength, fiber type and switch compatibility
4 ea
—
Rate needed
Long-run signal · Project-wideFOH to video wall4K60 · HDMI copper / active cableUse a manufacturer-rated optical HDMI or video-over-fiber system. Do not assume cascaded boosters will preserve format or HDCP.
2 path
2,200 ft
Rate needed
Labor · Project-wideProduction laborEnter role, crew count or day-rate basis
1 day
—
Rate needed
Transport · Project-wideTransport / deliveryEnter mileage, truck or delivery basis
1 allowance
—
Rate needed
MANUAL COMMERCIAL LINESLabor, transport and custom scope
Internal cost$0.00
Client subtotal$0.00
Discount−$0.00
Tax$0.00
Client total$0.00
Gross margin screen$0.00
DEVICE-LOCAL RELEASE: Pricing and quote settings currently save only in this browser. Account sync, durable revisions and controlled client share links belong to the future account release—not cookies.
AV STAGE TOOLS · CLIENT PROJECT
Untitled production
Venue / site TBD · Date TBD · Main room / stage
AV-DRAFTClient / host not enteredPrepared by EMP Software
Equipment units68
Known running load0 W
Power breakouts14
Network switches2
Client total$0.00
PROJECT SCOPE
Audio · Video · Lighting · Network · Power
This project view combines the declared equipment package with calculated cable, signal, power-distribution and network quantities. Final equipment availability and qualified approvals remain separate from the planning result.
MATERIAL TAKEOFF & COMMERCIAL SCOPE
Department / item
Qty / basis
Client amount
LED panelsLED / Display · Video wall · Enter exact panel model · Enter connector / adapter chain
48 ea
Rate pending
Line-array hangsAudio · Stage audio · Enter powered/passive model · Enter connector / adapter chain
2 ea
Rate pending
SubwoofersAudio · Stage audio · Enter powered/passive model · Enter connector / adapter chain
8 ea
Rate pending
Audio station devicesAudio · Audio station · Enter console, computer and outboard models · Enter connector / adapter chain
10 ea
Rate pending
Power breakout / outlet distributorPower distribution · Video wall · 58 outlets planned · 0 calculated branch circuits
10 ea
Rate pending
Power breakout / outlet distributorPower distribution · Stage audio · 12 outlets planned · 0 calculated branch circuits
2 ea
Rate pending
Power breakout / outlet distributorPower distribution · Audio station · 12 outlets planned · 0 calculated branch circuits
Audio station: Audio station devices: nameplate watts missing.
TERMS & EXCLUSIONS
Planning estimate valid for 30 days. Final availability, labor, taxes, freight, permits and verified equipment requirements may change the issued quote.
CREW HANDOFF
One plan, every department.
Save the text manifest on this browser or copy it into an email, rental request or production document.
What the planner refuses to guess
Power: Ampacity, connector rating, breaker selection, phase balance, neutral loading, grounding/bonding and generator paralleling require the exact equipment and qualified approval.
Video: HDMI has no universal cable-length limit. A 4K path outside its tested limit is not guaranteed to become a clean 1080p path; select a rated transport and test the entire chain.
Network: Port arithmetic cannot prove RF coverage, multicast performance, latency or protocol interoperability.
NEXT
Issue the plan with the paperwork.
Use the document library for call sheets, risk forms, run of show and load plans.